亚洲成a人无码亚洲成www牛牛-亚洲成成品网站源码中国有限公司-亚洲成色www久久网站夜月-亚洲成色在线综合网站-亚洲成色最大综合在线-亚洲成熟丰满熟妇高潮xxxxx

歡迎來到濱州恒通電力器材有限公司網站,我們竭誠為您服務

行業新聞
當前位置:首頁-資訊中心>行業新聞燃氣管道警示帶的三大埋設要點

燃氣管道警示帶的三大埋設要點

來源:http://www.gcshome.cn/ 發布時間:日期:2023-02-21 0
1.溝槽開挖。
1. Trench excavation.
(1)混凝土路面和瀝青路面的開挖應使用切割機切割。
(1) The excavation of concrete pavement and asphalt pavement shall be cut by cutting machine.
(2)管道溝槽應按設計規定的平面位置和標高開挖。當采用人工開挖且無地下水時,槽底預留值應為0.05~0.10m;管道安裝前應人工清底設計標高。
(2) The pipe trench shall be excavated according to the plane position and elevation specified in the design. When manual excavation is adopted and there is no underground water, the reserved value at the bottom of the trench shall be 0.05~0.10m; Before pipeline installation, the bottom shall be cleaned manually to the design elevation.
(3)管溝溝底寬度和工作尺寸,應根據現場實際情況和管道敷設方法確定。
(3) The width and working size of the trench bottom shall be determined according to the actual situation on site and the pipeline laying method.
(4)局部超挖部分應回填夯實。當溝底無地下水時,超挖在0.15m以內,可采用原土回填;超挖在0.15,以上,可采用石灰土處理。當溝底有地下水或水量較大時,應采用級配砂石或天然砂回填標高。超挖部分回填后壓實,其密實度應接近原地基天然土的密實度。
(4) The partial overbreak shall be backfilled and compacted. When there is no groundwater at the bottom of the ditch, the over-excavation is within 0.15m, and the original soil can be used for backfilling; If the overbreak is more than 0.15, lime soil can be used for treatment. When there is groundwater at the bottom of the ditch or there is a large amount of water, graded sand or natural sand shall be used to backfill to the elevation. The over-excavated part shall be compacted after backfilling, and its compactness shall be close to the compactness of the original foundation natural soil.
(5)在濕陷性黃土地區,不宜在雨期施工,或在施工時切實排除溝內積水,開挖時應在溝底預留值0.03~0.06m厚的土層進行壓實處理。
(5) In the collapsible loess area, construction should not be carried out in rainy season, or the accumulated water in the ditch should be effectively drained during construction. During excavation, a soil layer with a thickness of 0.03-0.06m should be reserved at the bottom of the ditch for compaction.
(6)溝底遇有廢棄構筑物、硬石、木頭、垃圾等雜物時必須,并應鋪一層厚度不小于0.15m砂土或素土,整平壓實及設計標高。
(6) In case of waste structures, hard rocks, wood, garbage and other sundries at the bottom of the ditch, they must be removed, and a layer of sand or plain soil with a thickness of not less than 0.15 m shall be paved, leveled and compacted to the design elevation.
(7)對軟土基及特殊腐蝕土壤,應按設計要求處理。
(7) Soft soil foundation and special corrosive soil shall be treated according to design requirements.
2.回填土。
2. Backfill.
(1)不得采用凍土、垃圾、木材及軟性物質回填。管道兩側及管頂以上0.5m內的回填土,不得含有碎石、磚塊等雜物,且不得采用灰土回填。距管頂0.5m以上的回填土中的石塊不得多于10%、直徑不得大于0.1m,且均勻分布。
(1) Frozen soil, garbage, wood and soft materials shall not be used for backfilling. The backfill on both sides of the pipe and within 0.5m above the pipe top shall not contain debris such as gravel and bricks, and shall not be backfilled with lime soil. The stones in the backfill soil more than 0.5m from the pipe top shall not be more than 10%, and the diameter shall not be more than 0.1m, and shall be evenly distributed.
燃氣管道警示帶
(2)溝槽的支撐應在管道兩側及管頂以上0.5m回填完畢并壓實后,在保證的情況下進行拆除,并應采取細砂填實縫隙。
(2) The support of the trench shall be removed under the condition of ensuring safety after backfilling and compaction on both sides of the pipe and 0.5m above the pipe top, and the gap shall be filled with fine sand.
(3.)溝槽回填時,應先回填管底懸空部位,再回填管道兩側。
(3) When backfilling the trench, the suspended part of the pipe bottom shall be backfilled first, and then both sides of the pipe shall be backfilled.
(4)回填土應分層壓實,每層虛鋪厚度宜為0.2~0.3m,管道兩側及管頂以上0.5m內的回填土必須采用人工壓實,管頂0.5m以上的回填土可采用小型機械壓實,每層虛鋪厚度宜為0.25~0.4m。
(4) Backfill soil shall be compacted by layers. The thickness of each layer should be 0.2~0.3m. Backfill soil on both sides of the pipeline and within 0.5m above the pipe top must be compacted manually. Backfill soil above 0.5m above the pipe top can be compacted by small machinery. The thickness of each layer should be 0.25~0.4m.
(5)回填土壓實后,應分層檢查密實度,并做好回填記錄。
(5) After the backfill is compacted, the compactness shall be checked layer by layer and the backfill records shall be made.
3.警示帶鋪設。
3. Laying of warning tape.
(1)埋設燃氣管道的沿線應連續鋪設警示帶。燃氣管道警示帶鋪設前應將鋪設面壓實,并平整的鋪設在管道的正上方,距管定的距離宜為0.3~0.5m,但不得鋪設于路基和路面內。
(1) Warning tapes shall be laid continuously along the buried gas pipeline. Before laying the gas pipeline warning tape, the laying surface shall be compacted and laid flat above the pipeline. The distance from the pipe should be 0.3~0.5m, but it shall not be laid in the subgrade and pavement.
(2)警示帶宜采用黃色聚乙烯等不易分解的材料,并印有明顯、牢固的警示語,字體不應小于100*100mm。
(2) The warning tape should be made of yellow polyethylene and other materials that are not easy to decompose, and should be printed with obvious and firm warning words. The font should not be less than 100 * 100mm.
當開挖施工時,如挖到燃氣警示帶,則表示在下方0.30.5米處有燃氣管道,起到了警示和保護作用。所以您對此有怎樣的需求歡迎來我們網站http://www.gcshome.cn咨詢!
During excavation, if the gas warning belt is dug, it means that there is a gas pipeline 0.3 to 0.5 meters below, which plays a role of warning and protection. So what's your need for this? Welcome to our website http://www.gcshome.cn consulting service

相關產品 / Related products

  • 地釘

    地釘

  • 地釘

    地釘

  • 警示樁

    警示樁

  • 警示樁

    警示樁

截屏,微信識別二維碼

主站蜘蛛池模板: 亚洲精品成人悠悠色影视 | 黄视频免费在线 | 看亚洲a级一级毛片 | 91 在线免费观看 | 99视频精品 | 成人精品鲁一区一区二区 | 国产精品久久久久久一区二区三区 | 精品在线免费观看 | 久久国产精品久久久 | 亚洲视频欧美视频 | 色综合天天综合网站中国 | 九九热线精品视频18 | 丨九色丨国产人妻 | 双程2电视剧在线观看完整泰剧 | 五月婷婷视频 | 中文字幕永久在线观看 | 成熟女人特级毛片www免费 | 欧美视频一区二区在线观看 | 午夜在线看片 | 日韩成人在线影院 | 日韩视频精品在线 | 国产精品99一区二区三区 | 国产1区| 亚洲一区二区三区四区五区午夜 | 末成年女av片一区二区 | 一区二区三区在线 | 欧 | 国产小视频在线 | 亚洲久热 | 波多野结衣中文字幕在线播放 | 国产日韩一区二区 | 欧美日本一区二区三区 | 色综合888 | 国产精品网站在线观看 | 亚洲九色| 91视频免费看 | 国产高清精品毛片基地 | 99久久99热这里只有精品 | 国产精品婷婷久青青原 | 中文字幕免费中文 | 激情aⅴ欧美一区二区欲海潮 | 久草在线视频在线观看 |